Government Cut Utility Tunnel and 54″ Sewer Forcemain

  • Government Cut Utility Tunnel and 54″ Sewer Forcemain
  • Government Cut Utility Tunnel and 54″ Sewer Forcemain
  • Government Cut Utility Tunnel and 54″ Sewer Forcemain
  • Government Cut Utility Tunnel and 54″ Sewer Forcemain

Project Description

Professional design, permitting, construction, testing, and commissioning of new utility pipelines, and the decommissioning and preparation for removal of the existing utility pipelines by others.

Replacement of the 20-inch water main under Fisherman’s Channel consisted of the following: Design/Build water main replacement based on a minimum eighty year life, installing two new water service pipes of 24-inch and 12-inch diameter, respectively, install new pipes in approximately 850 linear feet of new 60-inch minimum diameter micro-tunnel casing that shall commence at the Port of Miami on Port Island and terminate on the northern portion of Fisher Island, casing clearance at approximately EL (-) 90 feet to provide enough clearance for current and future dredging activities, installation of pipes within the micro-tunnel casing and fully encased in concrete grout, leaving no cavities for man access.

Pipe tapping connections at to location on the existing 20-inch water main and installation of new bi-directional flow meter at the Port of Miami. The 54-Inch Forcemain Replacement under Government Cut Channel consisted of a micro-tunnel of approximately 1,200 linear feet which included a new 54-inch pipe inside a 72-inch minimum diameter casing from the northern side of Fisher Island to a water location south of the City of Miami Beach via two deep shafts.

The casing clearance required approximately EL (-) 80 feet providing enough clearance for current and future dredging activities. The 54-inch carrier pipe was to be installed within the micro-tunnel casing, fully encase in concrete grout, leaving no cavities for man access.

A total of four taping connections with line stop schemes was required for the existing 54-inch sewerage force main. Two at the points of initiation and termination and two for a 36-inch temporary bypass to maintain uninterrupted service.

Task/Experience Description

Developed complete bid estimate (AACE Class 1 Estimate) for general contractor.

Details

PROJECT OWNER
Miami Dade Water and Sewer Department (MDWASD)
LOCATION
Miami, FL
DELIVERY SYSTEM
Design Build
PROJECT REFERENCE INFORMATION
Government Cut, Miami, Florida 1200 LF microtunnel for 54” sewer force main across main PortMiami channel.
PROJECT VALUE
$ 33 million
Cant find what you need?

See all services

Category: Tunnel, Utility, Water & Wastewater